Power equipment, not land, is the binding constraint on new data centers, favoring GE Vernova, Eaton, Quanta, Vertiv, Powell and Constellation. New heavy-duty gas turbine orders take about three years, with GE Vernova holding roughly 10 GW of slots across 2029 and 2030. Large power transformers exceed 160 weeks versus about 50 in 2021, and PJM projects online in 2025 averaged over seven years from queue to operation. Acreage can be released with a signature; turbines cannot. x.comÂ