Clearer North Carolina large-load rules could ultimately help WhiteFiber. Duke Energy's proposed settlement would require upfront infrastructure payments and transmission collateral from customers over 50MW signing after June 1, 2026. Its NC1 expansion from ~54MW to 99MW is likely unaffected, though another 200MW could cost more; ~30MW NC2/3 expansions may fall below the threshold. A regulator decision is due by mid-November, after the election, which may unclog stalled projects. x.comÂ